Generating Progress at Moxie Power Plant

SOURCE: Press EnterprisePHOTOS BY: Jimmy May


Cranes place modules on the site of the south generation station at the new Moxie Freedom Power Generation Plant, under construction along Mingle Inn Road in Salem Township. The modules were brought by train and off-loaded at the Riverview Block Co. They make the 3-mile trip to the power plant site on specifically designed flat-bed trucks.

Progress continues, at immediate right.

The cranes are standing modules on the south generation station, center left, and the switchyard is being constructed, top center. The natural gas pipeline that will supply the new power station can be seen running through the property from the top left corner to the bottom right.

Work on the new switch yard can be seen at far right. 

The switchyard is where the power generated at the plant will be transferred to the existing PPL transmission power lines, which run adjacent to the property.

Current News

MENU
 

Caithness Long Island Energy Center

TechnologyLocationNameplate RatingRolesInvestment Status
Combined CycleYaphank, NY350 MWDeveloper, Asset Manager, Operations Manager, Construction ManagerRealized 2026

Guernsey Power Station

TechnologyLocationNameplate RatingRolesInvestment Status
Combined CycleByesville, OH1,875 MWDeveloper, Asset Manager, Construction Manager, Operations ManagerRealized 2025

Moxie Freedom Generating Station

TechnologyLocationNameplate RatingRolesInvestment Status
Combined CycleBerwick, PA1050 MWDeveloper, Asset Manager, Operations Manager, Construction ManagerRealized 2025

Pasco Cogen

TechnologyLocationNameplate RatingRolesInvestment Status
Combined CycleDade City, FL121 MWAsset ManagerRealized 2007

Rumford Power

TechnologyLocationNameplate RatingRolesInvestment Status
Combined CycleRumford, ME265 MWAsset ManagerRealized 2007

Selkirk Cogen

TechnologyLocationNameplate RatingRolesInvestment Status
Combined CycleBethlehem, NY345 MWAsset ManagerRealized 2007

Sun Peak

TechnologyLocationNameplate RatingRolesInvestment Status
PeakerLas Vegas, NV220 MWAsset Manager, Operations ManagerRealized 2007

Tiverton Power

TechnologyLocationNameplate RatingRolesInvestment Status
Combined CycleTiverton, RI265 MWAsset ManagerRealized 2007

Blythe

TechnologyLocationNameplate RatingRolesInvestment Status
Combined CycleBlythe, CA507 MWDeveloperRealized 2007

Auburndale Power

TechnologyLocationNameplate RatingRolesInvestment Status
Combined CycleAuburndale, FL155 MWAsset Manager, Operations ManagerRealized 2007

Badger Creek

TechnologyLocationNameplate RatingRolesInvestment Status
Combined CycleBakersfield, CA50 MWAsset ManagerRealized 2007

Cherokee

TechnologyLocationNameplate RatingRolesInvestment Status
Combined CycleGaffney, SC95 MWDeveloper, Construction ManagerRealized 2007

Lake Cogen

TechnologyLocationNameplate RatingRolesInvestment Status
Combined CycleUmatilla, FL121 MWAsset ManagerRealized 2007

Mid-Georgia Cogen

TechnologyLocationNameplate RatingRolesInvestment Status
Combined CycleKathleen, GA305 MWAsset ManagerRealized 2007

Onondaga

TechnologyLocationNameplate RatingRolesInvestment Status
Combined CycleGeddes, NY91 MWAsset ManagerRealized 2007

Orlando Cogen

TechnologyLocationNameplate RatingRolesInvestment Status
Combined CycleOrange County, FL126 MWAsset ManagerRealized 2007
 

Caithness Long Island Energy Center

TechnologyLocationNameplate RatingRolesInvestment Status
Combined CycleYaphank, NY350 MWDeveloper, Asset Manager, Operations Manager, Construction ManagerRealized 2026